Agree - it's rarely "just the pistons" - since you are in there you may as well do the connecting and rod bearings. And of course you will get a look at the crank and the sealing rings may be nicked, and the main bearings may have some slop - plus, of course every gasket and seal you touch will have to be replaced.
Now, there is "total rebuild" kits out there in varying degrees of "completeness" - some with just rings, gaskets and bearings, others including pistons, main bearings etc. They generally range from 700'ish to 1200'ish bucks depending on how "complete" they are - but can give you a "rebuild in a box" set of parts should you go that route.
You still have to add on honing or boring of the cylinders. I always leave that to the experts at a machine shop - unless you do it all the time it's not worth cheaping out at this point - if you are going to tear down and replace anything, have a shop look after the cylinders (average about 50 bucks a hole, so figure $300 for a 6 cylinder).
Additionally, you still need to find the "cause" of the two toasted pistons - they are the "result". Most often it's a fuel system issue that caused them in the first place (clogged carbs is high on the list).
The parts to correct the cause are not part of the rebuild kit. Even if you go for a reman powerhead you will have to swap over your ignition, carbs etc, so whatever toasted the current one MUST be corrected.
(sound like I have rebuilt a couple?)
All in all, doing the work yourself, you can figure on dropping upwards of 2 grand to fully rebuild/restore a 6 cylinder. Now that may sound alot but you will get a "like new" motor and it's about 1/7th the cost of a new 150.
Food for thought...